ERCOT large-load integration
Use the current large-load process and documentation to establish the study path. A listing cannot promise a grid energization date.
Official process · reviewed · October 15, 2026Read less. Understand more.
Start with the takeaway. Open the source when you need the underlying detail, listing contact or official process.
Official starting points
Use the current large-load process and documentation to establish the study path. A listing cannot promise a grid energization date.
Official process · reviewed · October 15, 2026Locate pipeline and well leads, then contact the operator. Map presence does not establish pressure, spare capacity or tap rights.
Official mapping tool · reviewed · October 15, 2026Start with the applicable air-permit route for the chosen generating plant. Obtain a project-specific opinion before committing to a schedule.
Official permitting portal · reviewed · October 15, 2026Search the exact parcel, then have a civil engineer evaluate drainage and usable land. This portal did not return readable content during review; the link is provided as a diligence tool.
Official tool · content not retrieved · October 15, 2026Criterion-by-criterion evidence / Claude draft scoring restored
Compare all 21 original leads against ten criteria. Open any property to see its full calculation, draft gate results, rationale, concerns and source link. Switch weighting profiles to see how priorities change the result.
Scroll the matrix sideways for every criterion. Select “Breakdown” to see the calculation and documentation. Rankings include the displayed cohort; they do not remove gate failures automatically.
Weighted average: sum of (criterion rating × criterion weight) divided by included weight. The default substitutes 3 for the draft’s “3?” values. Conservative mode substitutes 1. Rated-only mode excludes unknown criteria and renormalizes the remaining weights. These alternative modes are sensitivity scenarios, not new factual ratings.
Assigned-rating coverage: the share of total weight with a numerical rating in the draft. This is not the percentage of independently verified evidence. The attachment does not supply a separate citation and rationale for every individual numeric cell; available support is the property-level listing link and draft narrative.
Gates: reproduced separately from the attachment so a weighted score cannot conceal a draft failure. Its acreage gate is a screening assumption, not a universal engineering standard. Current site-control status and a project-specific layout can change the result.
Profile differences: SEL weights total 100. Original brief weights total 98 and are normalized to 100%; the source maps climate to water, roads/workforce to access, tax to deal, and omits its separate security factor. The OpenAI profile totals 100. The twelve technical chapters remain available; reliability and climate do not have separate star columns in the draft’s ten-factor model.
Listing evidence
Each link opens the source with property details and broker contact options. Listing content is seller-reported; technical capacities have not been independently certified.
The most explicit gas-to-compute concept in this set. The advertised 200 MW is a concept, not demonstrated operating capacity.
Listing updated October 12, 2026. Review date: October 15, 2026.The lowest disclosed price in the active set. Enough gross land to investigate; gas deliverability remains the first question.
Listing updated December 11, 2025; reconfirm with broker. Review date: October 15, 2026.A large tract in a data-center corridor. Its listing is for support land, so campus-scale service still needs to be established.
Broker page marked Available when reviewed. Review date: October 15, 2026.A strong substation-adjacency lead. The decisive question is how much new load can actually connect, and when.
Broker page marked Active when reviewed. Review date: October 15, 2026.A premium-priced location near established infrastructure. The listing does not establish a transferable power allocation.
Listing updated October 12, 2026. Review date: October 15, 2026.Removed from the active shortlist. Retained to show why listing-status checks belong at the start of diligence.
Listing marked Off Market; updated August 25, 2026. Review date: October 15, 2026.From curiosity to commitment
The stages below are a planning sequence, not fixed durations or quoted fees. Work can overlap; the evidence should remain traceable.
Broker + project lead
Confirm availability, exact parcel and transaction terms. Identify the utility, pipeline operator and major physical constraints.
A tract identity, source log and explicit list of unknowns.
Pause if the seller cannot establish availability or identify the parcel.
Utility + gas operator + specialists
Obtain power and gas scope, carrier routes, preliminary permit advice and title/surface review.
Dated counterpart responses, a concept architecture and a first enabling-cost range.
Pause if the required service cannot be delivered on a workable schedule.
Counsel + owner + project team
Negotiate access and study rights, option conditions and an engineering scope aligned to the decision deadline.
An executed agreement and a funded, time-bounded diligence plan.
Do not let an option deadline force an unresolved technical assumption into a purchase decision.
Engineering + environmental + contractors
Complete survey, borings, environmental work, layout, equipment logistics and refined project costs.
A decision package with residual risks, commercial commitments and a commissioning path.
Advance only when the agreed investment gates are met; resolve exceptions explicitly.
The next step
Use this checklist for each shortlisted tract. Progress is saved only in this browser; checking a box does not verify the evidence.
0 of 9 diligence tasks checked
Method & definitions
This edition combines the Claude draft’s detailed tract analysis with the Muse draft’s plain-language criteria. It replaces speculative weighted stars with evidence labels, separates the visitor journey into three pages, and adds fresh listing checks. Five advertised properties form the reviewed comparison set. All 21 original leads are preserved in a separate searchable register with historical-data labels.
Generation technology, IT density, setbacks, redundancy, cooling and parcel geometry change the answer. Gross acreage is displayed for comparison; developable acreage must come from a survey and engineered test fit. No listed tract passes a land gate solely because it exceeds a selected acreage.
MW: megawatts of electrical power. IT load: power used by computing equipment. PUE: total facility power divided by IT equipment power. MMcf/day: million standard cubic feet of gas per day. Behind the meter: generation serving a facility on its side of the metering boundary; this does not by itself establish grid independence. NTP: notice to proceed.
Recheck listing status, asking price and broker statements before outreach or an offer. Replace claims with dated utility studies, agreements and permit records as they become available. This site does not automatically refresh from brokers.
More primary references
Explains the heat-removal chain and defines PUE and WUE. Use it to ask where heat leaves the campus and what drives water demand.
Open reference ↗Check the actual location’s nonattainment designation before a consultant determines the applicable permit requirements.
Open reference ↗Use published soils as a desktop screen and to focus investigation. It does not establish foundation design parameters for the campus.
Open reference ↗Follow process development and study discussions. Confirm the controlling rules and project classification with the utility.
Open reference ↗Answers that keep the investigation moving
No. Request the operator’s capacity, pressure, gas-quality and connection analysis. Easements and delivery rights must also be addressed.
Explore the evidence →No. Gross acreage does not show the buildable shape, drainage, setbacks or equipment layout. Use a phased test fit.
Explore the evidence →Yes. The internal loop and final heat-rejection system are separate design choices. Obtain a complete campus water balance.
Explore the evidence →No. Scoring an unknown as average can make an undocumented site appear competitive. Keep eligibility, commercial attractiveness and evidence completeness distinct.
Explore the evidence →They were not independently confirmed for this revision. They are not presented as binding requirements here. Consult the current agency record and project counsel.
Explore the evidence →